"How long until it arrives?" If the other party only replies with one number, it is basically unreliable. Real transit time is added up segment by segment; if any segment is ignored, what you calculate is a beautified answer.
Break transit time into five segments
| Stage | Description | Reference days |
|---|---|---|
| Stock preparation and consolidation | From when your production/packing is finished to when the cargo enters the warehouse and is loaded into the container | 1–3 days |
| Waiting for the ship and departure | Catching the sailing schedule, cut-off for customs and documentation, actual departure from port | 0–7 days (depending on sailing frequency) |
| Ocean voyage | This is the segment where express ships and general cargo ships differ the most | 11–35 days |
| Customs clearance and devanning | Arrival at port, declaration, release, container pickup, devanning and sorting | 3–8 days |
| Last mile delivery | Express or truck delivery to the warehouse; truck delivery also requires waiting for an appointment | 1–7 days |
The three places where you are most likely to fool yourself
First, "arrival at port" does not equal "arrival at warehouse." Many people mentally treat "the ship arrives in Los Angeles" as the finish line, but actually from arrival at port to the cargo truly sitting on Amazon shelves, there are still a series of steps in between: customs clearance, container pickup, devanning, delivery, and appointment.
Second, ignoring the "waiting for the ship" segment. If the sailing schedule is one sailing per week, missing the cut-off means waiting seven more days. This period is often assumed to be zero by default.
Third, planning based on the best-case scenario. Scheduling according to the ideal situation of off-season, favorable winds, no customs exam, and no queues—once peak season or a customs exam is encountered, the entire sales plan collapses.
A more reliable calculation method
The correct approach is: first get the normal segment-by-segment transit time by channel, then add buffers at key nodes—add in peak season, add when palletizing and appointments are required, add for sensitive categories. The final number is the number you can use for inventory planning.